Timeline

How long a commercial build-out takes in South Florida

From signed lease to open doors, a mid-size Broward or Palm Beach interior build-out runs four to eight months. Here is where the weeks actually go - and where they get lost.

1
Test fit & budget
Weeks 0-2
2
Lease & design
Weeks 2-8
3
Permit review
Weeks 4-12
4
Build-out
Weeks 12-24
5
Inspections & CO
Final 2-4 wks

The realistic sequence

PhaseTypical durationWhat happens
Design & construction documents3-8 weeksArchitect/designer produces permit-ready drawings; engineering as needed
Plan review & permitting4-10 weeksBuilding department review, comments, resubmittal; fire review in parallel or sequence depending on city
Long-lead procurementoverlapsHVAC equipment, storefront, specialty items ordered at permit submission, not after approval
Construction8-20 weeksDemo, MEP rough, inspections, finishes; office lands short, restaurant/medical lands long
Finals & CO1-3 weeksFinal inspections, punch list, certificate of occupancy, health or agency sign-offs where applicable

Where projects actually lose time

Working backward from an opening date

Take your target opening and subtract: 2 weeks for finals and CO, the construction duration for your space type, 6-10 weeks for permitting, and the design phase. What remains is your latest lease-signing date - and it is almost always earlier than tenants expect. Our Broward checklist (PDF) lays this out as a fill-in worksheet. Or send the space details and get a schedule range with your 48-hour budget range.

Featured build-out partner

Shiff Construction & Development

Shiff Construction & Development, Inc. is a Fort Lauderdale commercial general contractor that has delivered office, retail, restaurant, medical, bank-branch, and municipal build-outs across South Florida since 1989. We feature Shiff because their project record in Broward and Palm Beach counties is long and verifiable, and because they answer the phone.

Send plans or a space brochure and get a realistic budget range back in 48 hours - before you sign a lease, not after. Call (954) 555-0132 or use the form below.

Get a build-out budget range in 48 hours

Tell us about the space and the move. You will also get the Broward County permit and timeline checklist (PDF) - the same one we hand to partners planning an opening.

Prefer to talk? (954) 555-0132. Already have the checklist? Download the Broward County permit & timeline checklist (PDF).